Sabic UK Petrochemicals Ltd v Punj Lloyd Ltd [2013] EWHC 2916 (TCC) (10 October 2013)
SABIC was entitled to terminate the contract under clause 27.2.10 due to SCL's persistent failure to proceed with due diligence and under clause 27.2.5 due to SCL's financial deterioration. The warning letter was sufficient. SCL was not in repudiatory breach. SABIC's claim for costs to complete was established, but claims for lost revenue were excluded by clause 35.1. The proceeds of the performance and advance payment guarantees were to be brought into account before applying the contractual cap.
- Citation
- [2013] EWHC 2916 (TCC)
- Parties
- Claimant: SABIC UK Petrochemicals Limited (formerly Huntsman Petrochemicals (UK) Limited); Defendant/first Claimant (by Counterclaim): Punj Lloyd Limited; Second Claimant (by Counterclaim): Simon Carves Limited (In Administration)
- Jurisdiction
- England and Wales
- Judgment Date
- 10 October 2013
- Procedural Posture
- Commercial Construction Dispute (technology and Construction Court) / First Instance Judgment
- Outcome
- Judgment for SABIC (Claimant)
- Legal Topics
- Termination of Contract, Due Diligence in Construction Contracts, Performance Guarantees, Liquidated Damages, Implied Terms, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
SABIC UK Petrochemicals Limited (formerly Huntsman Petrochemicals (UK) Limited)
Claimant
Punj Lloyd Limited
Defendant/first Claimant (by Counterclaim)
Simon Carves Limited (In Administration)
Second Claimant (by Counterclaim)
Procedural Posture
Commercial Construction Dispute (technology and Construction Court) / First Instance Judgment
Legal Issues
- 1 Whether SABIC was entitled to terminate the contract for lack of due diligence and/or financial deterioration of SCL
- 2 Whether the warning letter of 3 October 2008 was sufficient under the contract
- 3 Whether SCL failed to proceed with due diligence during the warning period
Ratio Decidendi
SABIC was entitled to terminate the contract under clause 27.2.10 due to SCL's persistent failure to proceed with due diligence and under clause 27.2.5 due to SCL's financial deterioration. The warning letter was sufficient. SCL was not in repudiatory breach. SABIC's claim for costs to complete was established, but claims for lost revenue were excluded by clause 35.1. The proceeds of the performance and advance payment guarantees were to be brought into account before applying the contractual cap.
Court Disposition
Judgment for SABIC (Claimant)
Orders
- PLL/SCL's counterclaim dismissed
- SABIC awarded £11,797,514 (subject to separate judgment on statutory interest)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment