PBS Energo AS v Bester Generacion UK Ltd & Anor [2020] EWHC 223 (TCC) (07 February 2020)
On true construction of the contract, responsibility for site conditions, including subsurface conditions, was allocated to PBS. PBS was not entitled to terminate the contract for the reasons advanced. Bester's termination was not valid either, as the grounds relied upon did not satisfy the contractual requirements. Neither party lawfully terminated the contract; damages are determined accordingly.
- Citation
- [2020] EWHC 223 (TCC)
- Parties
- Claimant: PBS ENERGO A. S; First Defendant: BESTER GENERACION UK LTD; Second Defendant: BESTER GENERACION S. L. U; Part 20 Defendant: PRVNI BRNENSKA STROJIRNA VELKÁ BÍTEŠ A. S
- Jurisdiction
- England and Wales
- Judgment Date
- 07 February 2020
- Procedural Posture
- Construction Contract Dispute / Final Judgment After Trial
- Outcome
- Neither party lawfully terminated the contract; claims for damages are determined based on contractual allocation of risk and quantum findings.
- Legal Topics
- Termination of Contract, Allocation of Risk, Extension of Time, Liquidated Damages, Rectification, Quantum of Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PBS ENERGO A. S
Claimant
BESTER GENERACION UK LTD
First Defendant
BESTER GENERACION S. L. U
Second Defendant
PRVNI BRNENSKA STROJIRNA VELKÁ BÍTEŠ A. S
Part 20 Defendant
Procedural Posture
Construction Contract Dispute / Final Judgment After Trial
Legal Issues
- 1 Whether PBS lawfully terminated the contract with Bester
- 2 Whether Bester lawfully terminated the contract with PBS
- 3 Allocation of risk for ground conditions and permits
Ratio Decidendi
On true construction of the contract, responsibility for site conditions, including subsurface conditions, was allocated to PBS. PBS was not entitled to terminate the contract for the reasons advanced. Bester's termination was not valid either, as the grounds relied upon did not satisfy the contractual requirements. Neither party lawfully terminated the contract; damages are determined accordingly.
Court Disposition
Neither party lawfully terminated the contract; claims for damages are determined based on contractual allocation of risk and quantum findings.
Orders
- PBS's claim for damages is dismissed except as allowed for quantum items proven.
- Bester's counterclaim is dismissed except as allowed for quantum items proven.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment