Total M and E Services Ltd. v ABB Building Technologies Ltd. [2002] EWHC 248 (Technology) (26th February, 2002)
The mis-description of the referring party did not deprive the adjudicator of jurisdiction as all parties knew the true identity; the adjudicator had jurisdiction to award sums for additional works as the contract was in writing and variations were evidenced; costs of adjudication are not recoverable as damages;...
Source-derived case information.
- Citation
- [2002] EWHC 248 (Technology)
- Parties
- Claimant: Total M and E Services Limited; Defendant: ABB Building Technologies Limited (formerly ABB Steward Limited)
- Jurisdiction
- England and Wales
- Procedural Posture
- Summary Judgment Application (enforcement of Adjudicator's Award) / High Court (technology and Construction Court) Judgment
- Outcome
- Summary judgment granted for the claimant in the sum of £462,789.69 plus VAT; stay refused except for £121,087.50 plus VAT to be paid into court; costs of stay application to be paid by defendant.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Mis Description of Parties, Variation of Contract, Set Off and Counterclaim, Stay of Execution, Costs of Adjudication
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Total M and E Services Limited
Claimant
ABB Building Technologies Limited (formerly ABB Steward Limited)
Defendant
Procedural Posture
Summary Judgment Application (enforcement of Adjudicator's Award) / High Court (technology and Construction Court) Judgment
Legal Issues
- 1 Whether the adjudicator had jurisdiction given the mis-description of the referring party
- 2 Whether costs of adjudication are recoverable as damages
- 3 Whether the adjudicator had jurisdiction to award sums for additional works not expressly varied in writing
Ratio Decidendi
The mis-description of the referring party did not deprive the adjudicator of jurisdiction as all parties knew the true identity; the adjudicator had jurisdiction to award sums for additional works as the contract was in writing and variations were evidenced; costs of adjudication are not recoverable as damages; set-offs and counterclaims were invalid without a valid withholding notice; no special circumstances justified a stay of execution except for the sum relating to the unresolved set-off, which should be paid into court.
Court Disposition
Summary judgment granted for the claimant in the sum of £462,789.69 plus VAT; stay refused except for £121,087.50 plus VAT to be paid into court; costs of stay application to be paid by defendant.
Orders
- Summary judgment for £462,789.69 plus VAT to claimant
- £121,087.50 plus VAT to be paid into court pending further order
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment