National Grid Electricity Transmission Plc v ABB Ltd & Ors
The action should proceed to the close of pleadings and preliminary disclosure, but not be fixed for hearing until three months after exhaustion of all appeals against the Commission Decision. Immediate stay is not justified; preparation should continue to avoid prejudice to claimant and ensure readiness for trial. Siemens' request for further information is dismissed as premature.
- Parties
- Claimant: National Grid Electricity Transmission PLC; Defendant: ABB Limited; Defendant: ABB Power T & D Limited; Defendant: ABB Limited (subsidiary); Defendant: ABB Holdings Limited; Defendant: ABB Asea Brown Boveri Limited; Defendant: Alstom SA; Defendant: Alstom Limited; Defendant: Alstom UK Holdings Limited; Defendant: Alstom Holdings SA; Defendant: Areva SA; Defendant: Areva T & D Limited; Defendant: Areva T & D Holdings SA; Defendant: Siemens AG; Defendant: Siemens Transmission & Distribution Ltd; Defendant: VA Tech Reyrolle Distribution Limited; Defendant: Siemens PLC; Defendant: VA Tech (UK) Limited; Defendant: Siemens Holdings PLC; Defendant: VA Tech Schneider High Voltage GmbH; Defendant: VA Tech Transmission & Distribution & Co KEG; Defendant: Siemens Aktiengesellschaft Österreich
- Jurisdiction
- England and Wales
- Judgment Date
- 12 June 2009
- Procedural Posture
- Civil / Interlocutory Application for Stay and Further Information
- Outcome
- Application for immediate stay dismissed; action to proceed to close of pleadings and preliminary disclosure; Siemens' application for further information dismissed.
- Legal Topics
- Cartel Damages, Follow on Actions, Breach of Statutory Duty, Stay of Proceedings, Disclosure, Pleadings, Interest Calculation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
National Grid Electricity Transmission PLC
Claimant
ABB Limited
Defendant
ABB Power T & D Limited
Defendant
ABB Limited (subsidiary)
Defendant
ABB Holdings Limited
Defendant
ABB Asea Brown Boveri Limited
Defendant
Alstom SA
Defendant
Alstom Limited
Defendant
Alstom UK Holdings Limited
Defendant
Alstom Holdings SA
Defendant
Areva SA
Defendant
Areva T & D Limited
Defendant
Areva T & D Holdings SA
Defendant
Siemens AG
Defendant
Siemens Transmission & Distribution Ltd
Defendant
VA Tech Reyrolle Distribution Limited
Defendant
Siemens PLC
Defendant
VA Tech (UK) Limited
Defendant
Siemens Holdings PLC
Defendant
VA Tech Schneider High Voltage GmbH
Defendant
VA Tech Transmission & Distribution & Co KEG
Defendant
Siemens Aktiengesellschaft Österreich
Defendant
Procedural Posture
Civil / Interlocutory Application for Stay and Further Information
Legal Issues
- 1 When should a stay of proceedings be granted in a follow-on cartel damages action pending appeals against a European Commission decision?
- 2 Should the claimant be ordered to provide further information to the defendants at this stage?
Ratio Decidendi
The action should proceed to the close of pleadings and preliminary disclosure, but not be fixed for hearing until three months after exhaustion of all appeals against the Commission Decision. Immediate stay is not justified; preparation should continue to avoid prejudice to claimant and ensure readiness for trial. Siemens' request for further information is dismissed as premature.
Court Disposition
Application for immediate stay dismissed; action to proceed to close of pleadings and preliminary disclosure; Siemens' application for further information dismissed.
Orders
- Action not to be fixed for hearing against any defendant until three months after exhaustion of appeals to CFI or ECJ.
- Each defendant to serve defence by 26 June 2009.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment