North Midland Construction Plc v A E & E Lentjes UK Ltd
The enabling and civil works do not fall within the exclusion in s.105(2)(c)(i) but are construction operations under s.105(1), so the Act applies to the contracts. The court declines to make declarations regarding design responsibility and alleged changes to earth bonding due to lack of clarity and factual disputes.
- Parties
- Claimant: North Midland Construction PLC; Defendant: AE&E Lentjes UK Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 18 June 2009
- Procedural Posture
- Part 8 Claim / Judgment
- Outcome
- Declarations granted in part; Act applies to contracts. Declarations regarding earth bonding design responsibility and change denied.
- Legal Topics
- Statutory Interpretation, Applicability of Housing Grants Construction and Regeneration Act 1996, Construction Operations Definition, Process Engineering Exclusions, Design Responsibility
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
North Midland Construction PLC
Claimant
AE&E Lentjes UK Limited
Defendant
Procedural Posture
Part 8 Claim / Judgment
Legal Issues
- 1 Whether enabling and civil works fall within the exclusion in s.105(2)(c)(i) of the Housing Grants Construction and Regeneration Act 1996
- 2 Whether the works are 'construction operations' under s.105(1)
- 3 Responsibility for design of foundation earth bonding
Ratio Decidendi
The enabling and civil works do not fall within the exclusion in s.105(2)(c)(i) but are construction operations under s.105(1), so the Act applies to the contracts. The court declines to make declarations regarding design responsibility and alleged changes to earth bonding due to lack of clarity and factual disputes.
Court Disposition
Declarations granted in part; Act applies to contracts. Declarations regarding earth bonding design responsibility and change denied.
Orders
- Declaration that enabling and civil works are construction operations under s.105(1) and not excluded by s.105(2)(c)(i), so the Act applies.
- No declaration as to design responsibility for foundation earth bonding.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment