Plymouth & South West Co-Operative Society Ltd v Architecture, Structure & Management Ltd
ASM breached its duty of care by failing to advise Plymco on the risks of proceeding with an inadequately designed and costed contract and by not recommending a two-stage (Argos First) approach when it became clear that cost certainty could not be achieved. This breach caused Plymco's loss, as Plymco would have adopted the alternative approach if properly advised. Damages are awarded based on the difference between actual and hypothetical costs, plus identified savings that should have been advised.
- Parties
- Claimant: Plymouth & South West Co-operative Society Limited; Defendant: Architecture, Structure & Management Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 10 January 2006
- Procedural Posture
- Civil Contract/professional Negligence / Judgment After Full Trial
- Outcome
- Judgment for the Claimant (Plymco)
- Legal Topics
- Architect's Duty of Care, Cost Control in Construction Contracts, Two Stage Tendering, Damages for Breach of Contract, Causation and Quantification of Loss
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Plymouth & South West Co-operative Society Limited
Claimant
Architecture, Structure & Management Limited
Defendant
Procedural Posture
Civil Contract/professional Negligence / Judgment After Full Trial
Legal Issues
- 1 Did ASM breach its duty of care to Plymco in the procurement, tendering, and contract formation stages of the redevelopment project?
- 2 Was ASM negligent in failing to advise on cost risks and alternative procurement strategies?
- 3 Did ASM's breach cause Plymco's loss, and how should damages be quantified?
Ratio Decidendi
ASM breached its duty of care by failing to advise Plymco on the risks of proceeding with an inadequately designed and costed contract and by not recommending a two-stage (Argos First) approach when it became clear that cost certainty could not be achieved. This breach caused Plymco's loss, as Plymco would have adopted the alternative approach if properly advised. Damages are awarded based on the difference between actual and hypothetical costs, plus identified savings that should have been advised.
Court Disposition
Judgment for the Claimant (Plymco)
Orders
- ASM to pay Plymco damages of £1,392,088.00 for breach of contract and professional negligence.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment