Akzo Nobel UK Ltd v Arista Tubes Ltd
Once a valid notice under paragraph 11 of Schedule 7 of the BPA is served, it is no longer open to either party to require completion of the underleases; the effect of the notice is final and terminates the obligation to complete.
- Parties
- Claimant: Akzo Nobel UK Limited; Defendant: Arista Tubes Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 19 March 2009
- Procedural Posture
- Civil / Judgment
- Outcome
- claim dismissed
- Legal Topics
- Specific Performance, Construction of Contract Clauses, Termination of Obligations
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 1 Party arguments 2
Parties
Akzo Nobel UK Limited
Claimant
Arista Tubes Limited
Defendant
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether the claimant can require completion of underleases after service of a valid notice under paragraph 11 of Schedule 7 of the BPA
- 2 Interpretation of paragraph 11 of Schedule 7 of the BPA regarding termination and obligations
Ratio Decidendi
Once a valid notice under paragraph 11 of Schedule 7 of the BPA is served, it is no longer open to either party to require completion of the underleases; the effect of the notice is final and terminates the obligation to complete.
Court Disposition
claim dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment