PJ Pipe & Valve Co. Ltd. v Audco India Ltd.
PJV was the effective cause of the Bonny Island and Nanhai orders and is entitled to commission at 4.5% for Bonny Island phases 4, 5, and 6, and 3% for Nanhai. PJV qualifies as a commercial agent under the Regulations and is entitled to compensation for early termination. The commission is not limited to orders precisely identified in the Frame Agreement but covers all stainless steel and alloy gate, globe, and check valves for Nanhai. Compensation is calculated based on the average commission for one further successful introduction during the unexpired agency period.
- Parties
- Claimant: PJ Pipe & Valve Co. Limited; Defendant: Audco India Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 02 September 2005
- Procedural Posture
- Commercial/contractual Dispute / Judgment After Full Trial
- Outcome
- Judgment for the Claimant (PJV)
- Legal Topics
- Agency Agreements, Commission Entitlement, Repudiatory Breach, Commercial Agents (council Directive) Regulations 1993, Calculation of Compensation, Effective Cause Doctrine
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PJ Pipe & Valve Co. Limited
Claimant
Audco India Limited
Defendant
Procedural Posture
Commercial/contractual Dispute / Judgment After Full Trial
Legal Issues
- 1 What is the appropriate commission rate for Bonny Island Project phases 4 & 5?
- 2 Is PJV entitled to commission or damages for Bonny Island Project phase 6?
- 3 Was PJV a commercial agent under the Commercial Agents (Council Directive) Regulations 1993 and what compensation is due?
Ratio Decidendi
PJV was the effective cause of the Bonny Island and Nanhai orders and is entitled to commission at 4.5% for Bonny Island phases 4, 5, and 6, and 3% for Nanhai. PJV qualifies as a commercial agent under the Regulations and is entitled to compensation for early termination. The commission is not limited to orders precisely identified in the Frame Agreement but covers all stainless steel and alloy gate, globe, and check valves for Nanhai. Compensation is calculated based on the average commission for one further successful introduction during the unexpired agency period.
Court Disposition
Judgment for the Claimant (PJV)
Orders
- PJV awarded 4.5% commission on Bonny Island Project phases 4 & 5 (US$ 285,876.85)
- PJV awarded 4.5% commission on Bonny Island Project phase 6 (US$ 105,907.24)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment