Grove Developments Ltd v Balfour Beatty Regional Construction Ltd

Grove Developments Ltd v Balfour Beatty Regional Construction Ltd

Balfour Beatty had no contractual right to make or be paid in respect of IA24 (or any subsequent application) because the parties' agreed schedule provided for only 23 interim payments and no more, and no subsequent binding agreement or variation was reached to extend interim payments beyond those specified.

Source-derived case information.

Parties
Claimant: Grove Developments Ltd; Defendant: Balfour Beatty Regional Construction Ltd
Jurisdiction
England and Wales
Judgment Date
03 February 2016
Procedural Posture
Part 8 Claim / Judgment After Trial
Outcome
Claimant's claim for declaratory relief granted
Legal Topics
Interim Payments, Contract Interpretation, Estoppel, Variation of Contract, Payment Notices
Construction Law Contract Law Interim Payments Contract Interpretation Estoppel Variation of Contract Payment Notices

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 17 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Grove Developments Ltd

Claimant

Balfour Beatty Regional Construction Ltd

Defendant

Procedural Posture

Part 8 Claim / Judgment After Trial

  1. 1 Did Balfour Beatty have a contractual right to make IA24 (or any subsequent application) and to be paid in respect thereof?
  2. 2 If so, what was the final date for payment and did Grove Developments serve a valid Pay Less Notice?

Ratio Decidendi

Balfour Beatty had no contractual right to make or be paid in respect of IA24 (or any subsequent application) because the parties' agreed schedule provided for only 23 interim payments and no more, and no subsequent binding agreement or variation was reached to extend interim payments beyond those specified.

Court Disposition

Claimant's claim for declaratory relief granted

Orders

  • Declaration that Balfour Beatty had no contractual right to make IA24 (or any subsequent application) and no right to be paid in respect thereof
  • Declaration that Grove's Pay Less Notice of 15 September 2015 would have been valid if IA24 was contractually due