Taylor Woodrow Holdings Ltd v George Wimpey Southern Counties Ltd Rev 1
The court held that the effect of the contractual correspondence was to remove the Contractor’s qualification regarding unforeseen structural works (TC1), except for works to the external façade, which were covered by a provisional sum of £180,000.00. Therefore, the Employers did not retain the risk of unforeseen...
Source-derived case information.
- Parties
- Claimant: Taylor Woodrow Holdings Limited; Claimant: George Wimpey Southern Counties Limited; Defendant: Barnes & Elliott Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 03 July 2006
- Procedural Posture
- Application Under Arbitration Act 1996, Section 45 / Judgment on Preliminary Question of Law
- Outcome
- Application granted; preliminary objection dismissed; question of law determined
- Legal Topics
- Interpretation of Contract Terms, Allocation of Risk in Construction Contracts, Arbitration Procedure Under Section 45 Arbitration Act 1996
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Taylor Woodrow Holdings Limited
Claimant
George Wimpey Southern Counties Limited
Claimant
Barnes & Elliott Limited
Defendant
Procedural Posture
Application Under Arbitration Act 1996, Section 45 / Judgment on Preliminary Question of Law
Legal Issues
- 1 Did the Employers retain the risk of unforeseen works to the existing structure of the building which might be necessary before or as a consequence of the specified works?
- 2 Did the unforeseen structural works constitute a change in the Employers’ Requirements requiring evaluation under Clause 12 of the JCT WCD?
Ratio Decidendi
The court held that the effect of the contractual correspondence was to remove the Contractor’s qualification regarding unforeseen structural works (TC1), except for works to the external façade, which were covered by a provisional sum of £180,000.00. Therefore, the Employers did not retain the risk of unforeseen works to the existing structure, save for those works to the external façade subject to the provisional sum.
Court Disposition
Application granted; preliminary objection dismissed; question of law determined
Orders
- The court determines that the Employers did not retain the risk of unforeseen works to the existing structure, save for those works to the external façade which are the subject of the provisional sum of £180,000.00.
- The Contractor’s preliminary objection to the proceedings is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment