Taylor Woodrow Holdings Ltd v George Wimpey Southern Counties Ltd Rev 1 [2006] EWHC 1693 (TCC) (03 July 2006)
The court held that, based on the contract and incorporated correspondence, the Contractor assumed the risk for all necessary works to the structure, whether foreseen or unforeseen, except for works to the external façade covered by the provisional sum of £180,000.00. The Contractor's qualifications (TC1 and TC2) were removed, except as replaced by the provisional sum for external repairs. Therefore, the Employers did not retain the risk of unforeseen works to the existing structure, save for those works to the external façade subject to the provisional sum.
- Citation
- [2006] EWHC 1693 (TCC)
- Parties
- Claimant: Taylor Woodrow Holdings Limited; Claimant: George Wimpey Southern Counties Limited; Defendant: Barnes & Elliott Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 03 July 2006
- Procedural Posture
- Application Under Arbitration Act 1996, Section 45 / Judgment on Preliminary Question of Law Arising in Arbitral Proceedings
- Outcome
- Application granted; preliminary objection dismissed; question of law determined.
- Legal Topics
- Risk Allocation in Construction Contracts, Interpretation of Contract Terms, Arbitration Act 1996 Section 45, JCT Standard Form With Contractor's Design
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Taylor Woodrow Holdings Limited
Claimant
George Wimpey Southern Counties Limited
Claimant
Barnes & Elliott Limited
Defendant
Procedural Posture
Application Under Arbitration Act 1996, Section 45 / Judgment on Preliminary Question of Law Arising in Arbitral Proceedings
Legal Issues
- 1 Did the Employers retain the risk of unforeseen works to the existing structure of the building which might be necessary before or as a consequence of the specified works?
- 2 Did the allegedly unforeseen structural works constitute a change in the Employers' Requirements requiring evaluation under Clause 12 of the JCT WCD?
Ratio Decidendi
The court held that, based on the contract and incorporated correspondence, the Contractor assumed the risk for all necessary works to the structure, whether foreseen or unforeseen, except for works to the external façade covered by the provisional sum of £180,000.00. The Contractor's qualifications (TC1 and TC2) were removed, except as replaced by the provisional sum for external repairs. Therefore, the Employers did not retain the risk of unforeseen works to the existing structure, save for those works to the external façade subject to the provisional sum.
Court Disposition
Application granted; preliminary objection dismissed; question of law determined.
Orders
- The court determines that the Employers did not retain the risk of unforeseen works to the existing structure, save for those works to the external façade which are the subject of the provisional sum of £180,000.00.
- The Contractor's preliminary objection to these proceedings is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment