NKD MARITIME LIMITED v BART MARITIME (No 2) INC
NKD was not entitled to terminate the MOA under the force majeure clause because the seller was not ‘unable’ to transfer title within the meaning of the contract. The vessel’s arrival at the nearest accessible location constituted full performance under the MOA, and the delays caused by government restrictions did not amount to an inability to perform that would frustrate the commercial purpose of the contract. NKD’s purported termination was itself a repudiation, entitling Bart to retain the deposit.
- Parties
- Claimant: NKD Maritime Limited; Defendant: Bart Maritime (No. 2) Inc
- Jurisdiction
- England and Wales
- Judgment Date
- 24 June 2022
- Procedural Posture
- Commercial Contract Dispute / High Court Trial Judgment
- Outcome
- Claim dismissed; counterclaim allowed in part
- Legal Topics
- Force Majeure, Sale of Goods, Ship Recycling, Contract Termination, Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
NKD Maritime Limited
Claimant
Bart Maritime (No. 2) Inc
Defendant
Procedural Posture
Commercial Contract Dispute / High Court Trial Judgment
Legal Issues
- 1 Whether the termination of the Memorandum of Agreement (MOA) for the sale of a vessel was valid under the force majeure clause due to Covid-19 restrictions in India
- 2 Whether the seller was unable to transfer title in accordance with the contract due to government restraint
- 3 Whether the buyer was entitled to the return of the deposit under the MOA
Ratio Decidendi
NKD was not entitled to terminate the MOA under the force majeure clause because the seller was not ‘unable’ to transfer title within the meaning of the contract. The vessel’s arrival at the nearest accessible location constituted full performance under the MOA, and the delays caused by government restrictions did not amount to an inability to perform that would frustrate the commercial purpose of the contract. NKD’s purported termination was itself a repudiation, entitling Bart to retain the deposit.
Court Disposition
Claim dismissed; counterclaim allowed in part
Orders
- NKD’s claim is dismissed
- Bart is entitled to retain the Initial Payment (deposit) of US$4,264,723.13
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment