Dalkia Energy and Technical Services Ltd v Bell Group UK Ltd
Bell's standard terms and conditions were incorporated into the contract; clause 12.4 complied with section 108 of the 1996 Act; the adjudicator was validly appointed and had jurisdiction; only one dispute was referred; and the CPR Part 8 proceedings were not an abuse of process or inappropriate.
- Parties
- Claimant: Dalkia Energy and Technical Services Limited; Defendant: Bell Group UK Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 21 January 2009
- Procedural Posture
- Civil (construction/contract) / Judgment on CPR Part 8 Claim Regarding Adjudicator's Jurisdiction
- Outcome
- Claim dismissed; declarations sought by Dalkia refused; adjudicator has jurisdiction.
- Legal Topics
- Adjudication Under Construction Contracts, Jurisdiction of Adjudicator, Incorporation of Contract Terms, Compliance With Statutory Adjudication Provisions, Abuse of Process, CPR Part 8 Procedure
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dalkia Energy and Technical Services Limited
Claimant
Bell Group UK Limited
Defendant
Procedural Posture
Civil (construction/contract) / Judgment on CPR Part 8 Claim Regarding Adjudicator's Jurisdiction
Legal Issues
- 1 Whether Bell's standard terms and conditions were incorporated into the contract
- 2 Whether clause 12.4 of Bell's terms complied with section 108 of the Housing Grants, Construction and Regeneration Act 1996
- 3 Whether the adjudicator was properly appointed and had jurisdiction
Ratio Decidendi
Bell's standard terms and conditions were incorporated into the contract; clause 12.4 complied with section 108 of the 1996 Act; the adjudicator was validly appointed and had jurisdiction; only one dispute was referred; and the CPR Part 8 proceedings were not an abuse of process or inappropriate.
Court Disposition
Claim dismissed; declarations sought by Dalkia refused; adjudicator has jurisdiction.
Orders
- The claim is dismissed.
- The adjudicator has the necessary jurisdiction to determine the dispute between the parties.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment