Co-Operative Group Ltd v Birse Developments Ltd
Permission to re-amend was refused because Co-op's failure to plead its real case in mid-2012 caused significant and disproportionate delay and costs, contrary to the overriding objective. The repeated applications and amendments resulted in irrecoverable costs and prejudice to the defending parties, and further delay risked jeopardising the trial date. The administration of justice was harmed by the inefficient conduct of the litigation.
- Parties
- Claimant: Co-operative Group Limited; Defendant: Birse Developments Limited (In Liquidation); Third Party: Stuarts Industrial Flooring Limited (In Administration); Fourth Party: Jubb & Partners (a firm)
- Jurisdiction
- England and Wales
- Judgment Date
- 17 October 2013
- Procedural Posture
- Civil (construction/contract) / Application to Re Amend Particulars of Claim
- Outcome
- Application to re-amend refused
- Legal Topics
- Amendment of Pleadings, Overriding Objective, Proportionality of Costs, Case Management, Delay in Litigation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Co-operative Group Limited
Claimant
Birse Developments Limited (In Liquidation)
Defendant
Stuarts Industrial Flooring Limited (In Administration)
Third Party
Jubb & Partners (a firm)
Fourth Party
Procedural Posture
Civil (construction/contract) / Application to Re Amend Particulars of Claim
Legal Issues
- 1 Whether the Claimant should be granted permission to re-amend its Particulars of Claim to plead a claim for the cost of replacing warehouse floor slabs based on thickness defects
- 2 Whether the application offends the overriding objective of the Civil Procedure Rules as amended
- 3 Whether the repeated applications to amend and resulting delays and costs justify refusal of permission
Ratio Decidendi
Permission to re-amend was refused because Co-op's failure to plead its real case in mid-2012 caused significant and disproportionate delay and costs, contrary to the overriding objective. The repeated applications and amendments resulted in irrecoverable costs and prejudice to the defending parties, and further delay risked jeopardising the trial date. The administration of justice was harmed by the inefficient conduct of the litigation.
Court Disposition
Application to re-amend refused
Orders
- Co-op's application to re-amend its Particulars of Claim is dismissed.
- Legal teams to agree a revised timetable to bring the matter to trial in November 2014 if possible.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment