Co-Operative Group Ltd v Birse Developments Ltd & Ors
Birse’s causes of action in tort against Jubb and Geofirma accrued at the latest on practical completion, as Birse suffered measurable financial detriment and liability at that point; therefore, the claims are time barred under section 2 of the Limitation Act 1980. The failed assignment of Jubb’s warranty to Co-op without consent did not give rise to a trust, as the deed evidenced only an intention to assign, not to declare a trust.
- Parties
- Claimant: Co-operative Group Limited; Defendant: Birse Developments Limited (in Liquidation); Third Party: Stuarts Industrial Flooring Limited (In Administration); Fourth Party: Jubb & Partners (a firm); Fifth Party: Geofirma Soils Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 February 2014
- Procedural Posture
- Civil / Ruling on Preliminary Issues
- Outcome
- Claims in tort against Jubb and Geofirma are time barred; failed assignment did not create a trust.
- Legal Topics
- Limitation of Actions, Assignment of Warranties, Negligence, Collateral Warranties, Trusts Arising From Failed Assignments
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Co-operative Group Limited
Claimant
Birse Developments Limited (in Liquidation)
Defendant
Stuarts Industrial Flooring Limited (In Administration)
Third Party
Jubb & Partners (a firm)
Fourth Party
Geofirma Soils Engineering Limited
Fifth Party
Procedural Posture
Civil / Ruling on Preliminary Issues
Legal Issues
- 1 Whether Birse’s causes of action in tort against Jubb and Geofirma are time barred by section 2 of the Limitation Act 1980
- 2 Whether the attempt to assign the benefit of Jubb’s warranty to Co-op without consent gave rise to a trust in favour of Co-op
Ratio Decidendi
Birse’s causes of action in tort against Jubb and Geofirma accrued at the latest on practical completion, as Birse suffered measurable financial detriment and liability at that point; therefore, the claims are time barred under section 2 of the Limitation Act 1980. The failed assignment of Jubb’s warranty to Co-op without consent did not give rise to a trust, as the deed evidenced only an intention to assign, not to declare a trust.
Court Disposition
Claims in tort against Jubb and Geofirma are time barred; failed assignment did not create a trust.
Orders
- Birse’s causes of action in tort against Jubb and Geofirma are time barred by section 2 of the Limitation Act 1980.
- The attempt to assign the benefit of Jubb’s warranty to Co-op without consent did not give rise to a trust in favour of Co-op.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment