Castle Trustee Ltd & Ors v Bombay Palace Restaurant Ltd
The claimants are entitled to payment for additional works requested by the defendant outside the contract scope, assessed on a reasonable sum basis. The defendant is entitled to closure compensation for the entire period the restaurant was closed, as the closure was directly caused by the contract works, not by...
Source-derived case information.
- Parties
- Claimant: Castle Trustee Limited; Claimant: Enola Limited; Claimant: Liberty Nominees Limited; Claimant: Liberty Property (GP) Limited; Defendant: Bombay Palace Restaurant Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 06 July 2018
- Procedural Posture
- Civil (construction/commercial) / Final Judgment After Trial
- Outcome
- Judgment for both parties in part; claimants recover for some additional works; defendant recovers closure compensation; net balance to be calculated.
- Legal Topics
- Quantum Meruit, Contractual Interpretation, Variation of Contract, Extension of Time, Closure Compensation, Implied Terms
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Castle Trustee Limited
Claimant
Enola Limited
Claimant
Liberty Nominees Limited
Claimant
Liberty Property (GP) Limited
Claimant
Bombay Palace Restaurant Limited
Defendant
Procedural Posture
Civil (construction/commercial) / Final Judgment After Trial
Legal Issues
- 1 Whether the claimants are entitled to payment for additional or varied works requested by the defendant outside the original contract scope
- 2 Whether the defendant is entitled to closure compensation for the period the restaurant was closed
- 3 Proper construction of the agreement regarding variations and closure compensation
Ratio Decidendi
The claimants are entitled to payment for additional works requested by the defendant outside the contract scope, assessed on a reasonable sum basis. The defendant is entitled to closure compensation for the entire period the restaurant was closed, as the closure was directly caused by the contract works, not by additional works. The contract did not provide for an extension of time or variation mechanism that would reduce closure compensation for periods of delay caused by additional works.
Court Disposition
Judgment for both parties in part; claimants recover for some additional works; defendant recovers closure compensation; net balance to be calculated.
Orders
- Claimants entitled to payment for specified additional works as detailed in the judgment and schedule.
- Defendant entitled to closure compensation for the period 2 January 2012 to 19 May 2012, calculated at £784,571.43.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment