BNP Paribas Depository Services Limited & Anor v Briggs & Forrester Engineering Services Limited
The contract, as interpreted in light of its express terms, incorporated documents, and the factual matrix, placed full responsibility on B&F for all asbestos surveys and removal works necessary for the project, as well as for any structural strengthening works required to complete the stair pressurisation installation. The inclusion of the Woods quotation and Eton RAS did not carve out or limit this responsibility. B&F was not entitled to suspend or terminate the contract for employer prevention/default, as the suspension of works was caused by B&F's own failure to perform its contractual obligations. B&F's purported termination was a repudiatory breach, entitling BNP to treat the...
- Parties
- Claimant: BNP Paribas Depositary Services Limited; Claimant: BNP Paribas Depositary Services (Jersey) Limited; Defendant: Briggs & Forrester Engineering Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 18 November 2024
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment After Shorter Trials Scheme Trial
- Outcome
- Judgment for Claimant (BNP); declarations granted
- Legal Topics
- Contract Interpretation, Design and Build Contracts, Asbestos Removal Obligations, Termination of Contract, Repudiatory Breach
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
BNP Paribas Depositary Services Limited
Claimant
BNP Paribas Depositary Services (Jersey) Limited
Claimant
Briggs & Forrester Engineering Services Limited
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Judgment After Shorter Trials Scheme Trial
Legal Issues
- 1 Whether the contractor (B&F) was contractually responsible for further refurbishment asbestos surveys (RASs) and associated asbestos removal works (ARWs) beyond those identified in the Woods quotation and Eton RAS.
- 2 Whether the contractor was responsible for structural strengthening works to riser floors discovered during the project.
- 3 Whether the contractor was entitled to suspend and terminate the contract under clause 8.9.2/8.9.3 based on the employer's alleged prevention/default.
Ratio Decidendi
The contract, as interpreted in light of its express terms, incorporated documents, and the factual matrix, placed full responsibility on B&F for all asbestos surveys and removal works necessary for the project, as well as for any structural strengthening works required to complete the stair pressurisation installation. The inclusion of the Woods quotation and Eton RAS did not carve out or limit this responsibility. B&F was not entitled to suspend or terminate the contract for employer prevention/default, as the suspension of works was caused by B&F's own failure to perform its contractual obligations. B&F's purported termination was a repudiatory breach, entitling BNP to treat the...
Court Disposition
Judgment for Claimant (BNP); declarations granted
Orders
- Declaration that Briggs had no entitlement to serve the Purported Suspension Notice nor the Purported Termination Notice.
- Declaration that Briggs’ service of those notices, separately or together with its failure and refusal to proceed with the Works in accordance with the Contract in 2023, amounted to a repudiatory breach of the Contract.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment