Northumbrian Water Ltd v British Telecommunications Plc [2005] EWHC 2408 (TCC) (28 October 2005)
Pre-action disclosure was ordered only for categories of documents (design documents, health and safety plan, and contract documents) that were central to the anticipated dispute and which BT should have in their possession, as these met the requirements of CPR 31.16(3)(c) and (d). Disclosure was refused for other...
Source-derived case information.
- Citation
- [2005] EWHC 2408 (TCC)
- Parties
- Claimant: Northumbrian Water Ltd.; Defendant: British Telecommunications PLC
- Jurisdiction
- England and Wales
- Judgment Date
- 28 October 2005
- Procedural Posture
- Application for Pre Action Disclosure Under CPR 31.16 / Judgment on Application
- Outcome
- Application allowed in part and refused in part.
- Legal Topics
- Pre Action Disclosure, Disclosure of Documents, Civil Procedure Rules, Construction Disputes
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Northumbrian Water Ltd.
Claimant
British Telecommunications PLC
Defendant
Procedural Posture
Application for Pre Action Disclosure Under CPR 31.16 / Judgment on Application
Legal Issues
- 1 Whether the documents sought by the claimant satisfy the requirements for pre-action disclosure under CPR 31.16(3)
- 2 Whether the court should exercise its discretion to order pre-action disclosure of the requested documents
Ratio Decidendi
Pre-action disclosure was ordered only for categories of documents (design documents, health and safety plan, and contract documents) that were central to the anticipated dispute and which BT should have in their possession, as these met the requirements of CPR 31.16(3)(c) and (d). Disclosure was refused for other categories where documents did not exist, were peripheral, or did not meet the desirability or standard disclosure tests.
Court Disposition
Application allowed in part and refused in part.
Orders
- BT to disclose documents relating to the heading support design (category 4), the correct health and safety plan (category 5), and the main contract and subcontract documents relating to the tunnelling works (category 7).
- BT to make enquiries and inform NWL within seven days whether site diaries exist for the tunnelling works (category 6).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment