Westshield Civil Engineering Ltd & Anor v Buckingham Group Contracting Ltd [2013] EWHC 1825 (TCC) (28 June 2013)
The adjudicator's decision is not final and binding because Buckingham commenced court proceedings within 28 days of the decision, as required by the contract and CPR. However, the decision is binding pro tem and enforceable, and there are no grounds for a stay of execution as the defendant was aware of the...
Source-derived case information.
- Citation
- [2013] EWHC 1825 (TCC)
- Parties
- Claimant: Westshield Civil Engineering Limited; Claimant: Westshield Limited; Defendant: Buckingham Group Contracting Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 June 2013
- Procedural Posture
- Enforcement of Adjudicator's Decision (construction Contract) / Judgment on Enforcement Application
- Outcome
- Judgment for the claimant (Westshield Civil Engineering Limited) for the sum of £147,164.66; no stay of execution; no declaration of final binding effect of the adjudicator's decision.
- Legal Topics
- Adjudication Enforcement, Stay of Execution, Jurisdiction of Adjudicator, Commencement of Proceedings, Approbation and Reprobation
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Westshield Civil Engineering Limited
Claimant
Westshield Limited
Claimant
Buckingham Group Contracting Limited
Defendant
Procedural Posture
Enforcement of Adjudicator's Decision (construction Contract) / Judgment on Enforcement Application
Legal Issues
- 1 Whether the adjudicator's decision is enforceable given the commencement of court proceedings by the defendant
- 2 Whether a stay of execution should be granted due to the claimant's financial position
- 3 Whether the defendant is estopped from denying the identity of the subcontractor
Ratio Decidendi
The adjudicator's decision is not final and binding because Buckingham commenced court proceedings within 28 days of the decision, as required by the contract and CPR. However, the decision is binding pro tem and enforceable, and there are no grounds for a stay of execution as the defendant was aware of the claimant's financial position at the time of contracting and has not demonstrated a real risk of injustice.
Court Disposition
Judgment for the claimant (Westshield Civil Engineering Limited) for the sum of £147,164.66; no stay of execution; no declaration of final binding effect of the adjudicator's decision.
Orders
- Buckingham Group Contracting Limited to pay Westshield Civil Engineering Limited £147,164.66 (plus VAT if registered)
- No stay of execution granted
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment