Hyder Consulting (UK) Ltd v Carillion Construction Ltd
Carillion failed to demonstrate that the adjudicator's failure to notify them of his methodology or figures for the Target Cost calculation amounted to a material breach of natural justice. The calculation of the Target Cost was always in issue, both parties had the opportunity to make submissions, and the figures used were available to Carillion. Even if Carillion had made the points now raised, the outcome would not have changed. Therefore, summary judgment is granted for Hyder.
- Parties
- Claimant: Hyder Consulting (UK) Limited; Defendant: Carillion Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 13 July 2011
- Procedural Posture
- Civil (commercial Construction Dispute) / Application for Summary Judgment to Enforce Adjudicator's Decision
- Outcome
- Summary judgment for the claimant (Hyder) enforcing the adjudicator's decision.
- Legal Topics
- Adjudication Enforcement, Natural Justice, Summary Judgment, Pain/gain Share Provisions, Target Cost Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hyder Consulting (UK) Limited
Claimant
Carillion Construction Limited
Defendant
Procedural Posture
Civil (commercial Construction Dispute) / Application for Summary Judgment to Enforce Adjudicator's Decision
Legal Issues
- 1 Whether the adjudicator's decision should be enforced despite alleged breach of natural justice
- 2 Whether the adjudicator failed to notify parties of his methodology and figures for Target Cost calculation
- 3 Whether any breach of natural justice was material to the outcome
Ratio Decidendi
Carillion failed to demonstrate that the adjudicator's failure to notify them of his methodology or figures for the Target Cost calculation amounted to a material breach of natural justice. The calculation of the Target Cost was always in issue, both parties had the opportunity to make submissions, and the figures used were available to Carillion. Even if Carillion had made the points now raised, the outcome would not have changed. Therefore, summary judgment is granted for Hyder.
Court Disposition
Summary judgment for the claimant (Hyder) enforcing the adjudicator's decision.
Orders
- Carillion to pay Hyder £3,104,399.74 plus interest as awarded by the adjudicator.
- Carillion to pay 50% of the adjudicator's fees as ordered.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment