Costain Ltd v Charles Haswell & Partners Ltd
A binding contract existed between Costain and Haswell by 3 October 2002, either by express agreement or by conduct. Haswell breached its duty of care by misinterpreting site investigation data, failing to account for soil variability, and negligently recommending a pre-loading ground treatment scheme inappropriate for the site, without adequate warnings or design documentation. Clause 7.4 imposed strict liability only for works incorporated into the permanent works, not for the abandoned surcharge scheme. The negligent advice caused Costain to incur additional costs, but Costain failed to prove entitlement to most prolongation and third-party settlement costs due to lack of evidence and...
- Parties
- Claimant: Costain Limited; Defendant: Charles Haswell & Partners Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 24 September 2009
- Procedural Posture
- Civil (contract/negligence) / Judgment After Full Trial
- Outcome
- Judgment for Claimant in part; damages awarded for direct additional costs and piling only; most other claims dismissed.
- Legal Topics
- Formation of Contract, Strict Liability in Consultancy Agreements, Professional Duty of Care, Damages for Breach of Contract, Causation and Quantum of Damages, Double Recovery, Costs Orders
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Costain Limited
Claimant
Charles Haswell & Partners Limited
Defendant
Procedural Posture
Civil (contract/negligence) / Judgment After Full Trial
Legal Issues
- 1 Whether a binding contract existed between Costain and Haswell for consultancy services
- 2 Whether Haswell owed and breached a duty of care in its design recommendations
- 3 Whether Clause 7.4 of the Consultancy Agreement imposed strict liability
Ratio Decidendi
A binding contract existed between Costain and Haswell by 3 October 2002, either by express agreement or by conduct. Haswell breached its duty of care by misinterpreting site investigation data, failing to account for soil variability, and negligently recommending a pre-loading ground treatment scheme inappropriate for the site, without adequate warnings or design documentation. Clause 7.4 imposed strict liability only for works incorporated into the permanent works, not for the abandoned surcharge scheme. The negligent advice caused Costain to incur additional costs, but Costain failed to prove entitlement to most prolongation and third-party settlement costs due to lack of evidence and...
Court Disposition
Judgment for Claimant in part; damages awarded for direct additional costs and piling only; most other claims dismissed.
Orders
- Haswell to pay Costain £163,478.51 in damages plus interest at 0.5% below base rate from 20 November 2002, with a 50% reduction for 12 months of unreasonable delay.
- Haswell to pay 38.75% of Costain’s costs, assessed on the standard basis, plus interest from 1 June 2008.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment