Swift v Carpenter
Appellant entitled to uplift on damages, indemnity costs from 23 July 2019, and interest at 4.5% on additional damages and costs. Costs of application to call expert witnesses awarded to respondent; costs of application to admit respondent's witness not awarded. Permission to appeal refused.
- Parties
- Appellant: Charlotte Swift; Respondent: Malcolm Carpenter; Intervener: Personal Injuries Bar Association
- Jurisdiction
- England and Wales
- Judgment Date
- 06 November 2020
- Procedural Posture
- Civil Appeal / Judgment on Costs and Permission to Appeal
- Outcome
- Appellant awarded costs and interest as specified; permission to appeal refused.
- Legal Topics
- Costs, Interest, Part 36 Offers, Permission to Appeal
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Charlotte Swift
Appellant
Malcolm Carpenter
Respondent
Personal Injuries Bar Association
Intervener
Procedural Posture
Civil Appeal / Judgment on Costs and Permission to Appeal
Legal Issues
- 1 Entitlement to costs following Part 36 offer
- 2 Appropriate rate of interest on damages and costs
- 3 Responsibility for costs of applications regarding expert evidence
Ratio Decidendi
Appellant entitled to uplift on damages, indemnity costs from 23 July 2019, and interest at 4.5% on additional damages and costs. Costs of application to call expert witnesses awarded to respondent; costs of application to admit respondent's witness not awarded. Permission to appeal refused.
Court Disposition
Appellant awarded costs and interest as specified; permission to appeal refused.
Orders
- Appellant awarded uplift on damages of £65,095.65 for beating Part 36 offer.
- Appellant awarded indemnity costs from 23 July 2019.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment