Lee v Chartered Properties (Building) Ltd [2010] EWHC 1540 (TCC) (25 June 2010)
The adjudicator's decision was unenforceable because it was not delivered as soon as possible after being reached, as required by the Scheme for Construction Contracts. There were also triable issues regarding the validity of the adjudicator's appointment and whether the parties had settled their claims prior to...
Source-derived case information.
- Citation
- [2010] EWHC 1540 (TCC)
- Parties
- Claimant: Lorraine Lee; Defendant: Chartered Properties (Building) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 25 June 2010
- Procedural Posture
- Claim to Set Aside Statutory Demand and Challenge Adjudicator's Decision / Summary Judgment Application
- Outcome
- Adjudicator's decision declared unenforceable; summary judgment refused for both parties; triable issues remain for trial.
- Legal Topics
- Adjudication Enforcement, Statutory Demand, Jurisdiction of Adjudicator, Settlement Agreements, Natural Justice, Summary Judgment
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lorraine Lee
Claimant
Chartered Properties (Building) Limited
Defendant
Procedural Posture
Claim to Set Aside Statutory Demand and Challenge Adjudicator's Decision / Summary Judgment Application
Legal Issues
- 1 Whether the adjudicator's decision was enforceable given alleged late delivery
- 2 Whether the adjudicator was validly appointed
- 3 Whether a dispute had crystallised
Ratio Decidendi
The adjudicator's decision was unenforceable because it was not delivered as soon as possible after being reached, as required by the Scheme for Construction Contracts. There were also triable issues regarding the validity of the adjudicator's appointment and whether the parties had settled their claims prior to adjudication, precluding summary judgment.
Court Disposition
Adjudicator's decision declared unenforceable; summary judgment refused for both parties; triable issues remain for trial.
Orders
- The adjudicator's decision dated 13 November 2009 and issued 16 November 2009 is unenforceable.
- No summary judgment granted to either party.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment