The University of Manchester v John McAslan and Partners Ltd & Anor
Costs in the case is the fair order given the partial success of both parties and the ongoing nature of the litigation.
- Parties
- Claimant: The University of Manchester; First Defendant: John McAslan and Partners Limited; Second Defendant: Laing O’Rourke Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 December 2020
- Procedural Posture
- Civil / Post Application Costs Determination
- Outcome
- costs in the case
- Legal Topics
- Costs, Pleadings, Case Management
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 2 Party arguments 2
Parties
The University of Manchester
Claimant
John McAslan and Partners Limited
First Defendant
Laing O’Rourke Construction Limited
Second Defendant
Procedural Posture
Civil / Post Application Costs Determination
Legal Issues
- 1 allocation of costs following applications
- 2 adequacy of particulars of claim
- 3 management of pleadings
Ratio Decidendi
Costs in the case is the fair order given the partial success of both parties and the ongoing nature of the litigation.
Court Disposition
costs in the case
Orders
- First Defendant's costs to be costs in the case
- Second Defendant's costs for work prior to Cross-Referencing Document to be costs in the case
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment