Edenbooth Ltd v Cre8 Developments Ltd
The adjudicator had jurisdiction because the works were construction operations under the Act, the residential occupier exemption did not apply to the defendant company, and there was no procedural unfairness. The adjudicator's decision is enforceable.
- Parties
- Claimant: Edenbooth Limited; Defendant: Cre8 Developments Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 13 March 2008
- Procedural Posture
- Summary Judgment Application for Enforcement of Adjudicator's Decision / Judgment
- Outcome
- Judgment for the claimant
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Residential Occupier Exemption, Natural Justice
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Edenbooth Limited
Claimant
Cre8 Developments Limited
Defendant
Procedural Posture
Summary Judgment Application for Enforcement of Adjudicator's Decision / Judgment
Legal Issues
- 1 Whether the adjudicator had jurisdiction under the Housing Grants (Construction and Regeneration) Act 1998
- 2 Whether the works were construction operations under the Act
- 3 Whether the residential occupier exemption applied
Ratio Decidendi
The adjudicator had jurisdiction because the works were construction operations under the Act, the residential occupier exemption did not apply to the defendant company, and there was no procedural unfairness. The adjudicator's decision is enforceable.
Court Disposition
Judgment for the claimant
Orders
- Defendant to pay £18,343.06 plus VAT on the fee element and interest of £245.23, total £18,928.19
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment