WSP Cel Ltd v Dalkia Utilities Services Plc
The Consent Agreement, by its clear terms, extended the time for referring any aspect of the dispute to adjudication and gave the adjudicator exclusive jurisdiction to determine the effect and interpretation of the agreement, including jurisdictional issues. The parties agreed to be bound by the adjudicator's decision unless and until revised by the court. Therefore, Dalkia did not have real prospects of successfully defending the enforcement of the adjudicator’s decision, and WSP was entitled to summary judgment.
- Parties
- Claimant: WSP CEL Limited; Defendant: Dalkia Utilities Services PLC
- Jurisdiction
- England and Wales
- Judgment Date
- 28 August 2012
- Procedural Posture
- Civil Commercial/construction / Summary Judgment Application
- Outcome
- Summary judgment granted for the claimant (WSP) enforcing the adjudicator’s decision.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Interpretation of Consent Agreements, Time Limits for Dispute Referral
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
WSP CEL Limited
Claimant
Dalkia Utilities Services PLC
Defendant
Procedural Posture
Civil Commercial/construction / Summary Judgment Application
Legal Issues
- 1 Whether the adjudicator had jurisdiction to determine the dispute under the Consent Agreement
- 2 Whether the Consent Agreement extended the time for referring disputes to adjudication
- 3 Whether the adjudicator's decision is binding and enforceable
Ratio Decidendi
The Consent Agreement, by its clear terms, extended the time for referring any aspect of the dispute to adjudication and gave the adjudicator exclusive jurisdiction to determine the effect and interpretation of the agreement, including jurisdictional issues. The parties agreed to be bound by the adjudicator's decision unless and until revised by the court. Therefore, Dalkia did not have real prospects of successfully defending the enforcement of the adjudicator’s decision, and WSP was entitled to summary judgment.
Court Disposition
Summary judgment granted for the claimant (WSP) enforcing the adjudicator’s decision.
Orders
- WSP is entitled to summary judgment for the sums awarded by the adjudicator in the decision.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment