RESOURCE RECOVERY SOLUTIONS (DERBYSHIRE) LIMITED v DERBYSHIRE COUNTY COUNCIL & Anor.
The Claimant succeeded on the summary judgment/strike out application and is entitled to its costs on the standard basis, not indemnity, as the Defendants' conduct was not unreasonable to a high degree. For the Reply Strike Out, the Defendants are entitled to their costs up to the Amended Reply, and the Claimant is...
Source-derived case information.
- Parties
- Claimant: Resource Recovery Solutions (Derbyshire) Limited; Defendant: Derbyshire County Council; Defendant: Derby City Council
- Jurisdiction
- England and Wales
- Judgment Date
- 11 September 2024
- Procedural Posture
- Civil / Post Summary Judgment/strike Out Application; Costs Determination
- Outcome
- Claimant awarded costs of summary judgment/strike out application on standard basis; Defendants awarded costs of Reply Strike Out up to Amended Reply; Claimant awarded costs post-Amended Reply, all on standard basis.
- Legal Topics
- Costs, Summary Judgment, Strike Out, Indemnity Costs
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Resource Recovery Solutions (Derbyshire) Limited
Claimant
Derbyshire County Council
Defendant
Derby City Council
Defendant
Procedural Posture
Civil / Post Summary Judgment/strike Out Application; Costs Determination
Legal Issues
- 1 Whether costs should be awarded on an indemnity or standard basis following dismissal of summary judgment/strike out application
- 2 Appropriate allocation of costs for different periods of the strike out application
Ratio Decidendi
The Claimant succeeded on the summary judgment/strike out application and is entitled to its costs on the standard basis, not indemnity, as the Defendants' conduct was not unreasonable to a high degree. For the Reply Strike Out, the Defendants are entitled to their costs up to the Amended Reply, and the Claimant is entitled to its costs thereafter, all on the standard basis.
Court Disposition
Claimant awarded costs of summary judgment/strike out application on standard basis; Defendants awarded costs of Reply Strike Out up to Amended Reply; Claimant awarded costs post-Amended Reply, all on standard basis.
Orders
- Claimant to recover costs of summary judgment/strike out application on standard basis.
- Defendants to recover costs of Reply Strike Out application up to service of Amended Reply on standard basis.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment