Tata Consultancy Services Limited v Disclosure and Barring Service
The court corrected the judgment to limit TCS's entitlement to delay damages to 12 days, not 98, due to internal inconsistency and contractual construction. TCS was not entitled to statutory interest under the 1998 Act for disputed invoices, as the contract ousted such entitlement and no qualifying debt arose. TCS was permitted to amend to claim VAT, but not statutory interest. TCS was awarded 20% of its costs, reflecting minimal net success unrelated to most litigation costs.
- Parties
- Claimant: Tata Consultancy Services Limited; Defendant: Disclosure and Barring Service
- Jurisdiction
- England and Wales
- Judgment Date
- 08 January 2024
- Procedural Posture
- Commercial Contract Dispute / Post Judgment Consequential Matters
- Outcome
- Judgment corrected; TCS awarded limited delay damages, VAT permitted, statutory interest claim refused, TCS awarded 20% of costs, interim payment ordered.
- Legal Topics
- Interest on Debts, Delay Damages, Costs, Contractual Interpretation, VAT, Remedies
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tata Consultancy Services Limited
Claimant
Disclosure and Barring Service
Defendant
Procedural Posture
Commercial Contract Dispute / Post Judgment Consequential Matters
Legal Issues
- 1 Correction of judgment for internal inconsistency in delay damages
- 2 Entitlement to interest under Late Payment of Commercial Debts (Interest) Act 1998
- 3 Whether contractual clauses oust statutory interest
Ratio Decidendi
The court corrected the judgment to limit TCS's entitlement to delay damages to 12 days, not 98, due to internal inconsistency and contractual construction. TCS was not entitled to statutory interest under the 1998 Act for disputed invoices, as the contract ousted such entitlement and no qualifying debt arose. TCS was permitted to amend to claim VAT, but not statutory interest. TCS was awarded 20% of its costs, reflecting minimal net success unrelated to most litigation costs.
Court Disposition
Judgment corrected; TCS awarded limited delay damages, VAT permitted, statutory interest claim refused, TCS awarded 20% of costs, interim payment ordered.
Orders
- Correction of delay damages to 12 days (£50,279.60 manpower, £1,222,716.80 non-manpower)
- Net sum payable by DBS to TCS: £3,682,024.40 plus applicable VAT
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment