Chenco Chemical Engineering And Consulting GmbH v DO Fluoride Chemicals Co. Ltd
DFD failed to prove by credible contemporaneous evidence that it made material changes to its reactors or core process after the award; the alleged redesign was not genuine and was fabricated during the present litigation. The court has jurisdiction to determine whether DFD ceased using Chenco’s Technology. Chenco is entitled to enforce the award for the post-award period, including liquidated damages and interest.
- Parties
- Claimant: Chenco Chemical Engineering and Consulting GmbH; Defendant: Do Fluoride Chemicals Co. Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 26 April 2021
- Procedural Posture
- Commercial Enforcement of Arbitral Award / Judgment After Trial on Post Award Enforcement
- Outcome
- Judgment for Claimant; enforcement of arbitral award for post-award period granted
- Legal Topics
- Enforcement of Foreign Arbitral Awards, Breach of Contract, Liquidated Damages, Jurisdiction of Enforcement Court
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Chenco Chemical Engineering and Consulting GmbH
Claimant
Do Fluoride Chemicals Co. Ltd
Defendant
Procedural Posture
Commercial Enforcement of Arbitral Award / Judgment After Trial on Post Award Enforcement
Legal Issues
- 1 Whether DFD continued to use Chenco’s Technology after the arbitral award and is liable for further liquidated damages
- 2 Whether the English court has jurisdiction to determine if DFD ceased use of Chenco’s Technology post-award
- 3 Whether DFD’s alleged reactor redesign in 2013 was genuine and sufficient to avoid liability under the award
Ratio Decidendi
DFD failed to prove by credible contemporaneous evidence that it made material changes to its reactors or core process after the award; the alleged redesign was not genuine and was fabricated during the present litigation. The court has jurisdiction to determine whether DFD ceased using Chenco’s Technology. Chenco is entitled to enforce the award for the post-award period, including liquidated damages and interest.
Court Disposition
Judgment for Claimant; enforcement of arbitral award for post-award period granted
Orders
- DFD to pay Chenco €4,000,000 in liquidated damages for May 2013 to August 2016
- DFD to pay default interest as awarded by the tribunal, with updated calculation to be provided
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment