General Medical Council v Adekola

General Medical Council v Adekola

The extension of the interim order of conditions for nine months is justified due to the seriousness of the allegations, the need to protect the public, and reasonable expedition by the GMC. The court declines to vary conditions at this stage, as the matter will revert to the Interim Orders Panel. Costs are awarded to the GMC as their conduct was faultless and the costs claimed are reasonable.

Parties
Claimant: General Medical Council; Defendant: Dr Rapinder Adekola
Jurisdiction
England and Wales
Judgment Date
20 February 2013
Procedural Posture
Judicial Review / Application for Extension of Interim Order
Outcome
Application for extension of interim order granted; costs awarded to GMC.
Legal Topics
Fitness to Practise, Interim Orders, Professional Misconduct, Costs Assessment

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

General Medical Council

Claimant

Dr Rapinder Adekola

Defendant

Procedural Posture

Judicial Review / Application for Extension of Interim Order

  1. 1 Whether an extension of the interim order of conditions is justified under section 41A(6) Medical Act 1983
  2. 2 Whether the court should vary the conditions imposed
  3. 3 Whether costs should be awarded to the GMC

Ratio Decidendi

The extension of the interim order of conditions for nine months is justified due to the seriousness of the allegations, the need to protect the public, and reasonable expedition by the GMC. The court declines to vary conditions at this stage, as the matter will revert to the Interim Orders Panel. Costs are awarded to the GMC as their conduct was faultless and the costs claimed are reasonable.

Court Disposition

Application for extension of interim order granted; costs awarded to GMC.

Orders

  • Extension of interim order of conditions for nine months until 27 November 2013.
  • Summary assessment of costs in the sum of £1,090.80 awarded to GMC.