Melhuish & Saunders Ltd v Hurden & Anor
The claimant breached implied contractual terms by failing to construct the property to a standard sufficient to obtain a final Building Regulations certificate, particularly in relation to the installation of wall ties and lintels. The appropriate measure of damages is the cost of remedial works based on the 'budget cost' option, including complete re-pointing, as well as damages for distress, inconvenience, and temporary relocation. It was reasonable for the defendants to refuse to allow the claimant to carry out the remedial works due to loss of trust. The counterclaim exceeds the amount of the claim, resulting in the claim failing by way of set-off.
- Parties
- Claimant: Melhuish & Saunders Limited; Defendant: Edward Charles Hurden; Defendant: Elizabeth Ann Hurden
- Jurisdiction
- England and Wales
- Judgment Date
- 19 October 2012
- Procedural Posture
- Civil (construction Dispute) / Judgment After Trial
- Outcome
- Claim dismissed by set-off; counterclaim allowed in part
- Legal Topics
- Building Contracts, Defective Works, Remedial Damages, Implied Terms, Mitigation of Loss, Damages for Distress and Inconvenience
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Melhuish & Saunders Limited
Claimant
Edward Charles Hurden
Defendant
Elizabeth Ann Hurden
Defendant
Procedural Posture
Civil (construction Dispute) / Judgment After Trial
Legal Issues
- 1 Whether the claimant is entitled to payment for the final invoice for building works
- 2 Whether the works were defective and in breach of contract
- 3 Whether the defendants are entitled to damages for remedial works, distress, and relocation
Ratio Decidendi
The claimant breached implied contractual terms by failing to construct the property to a standard sufficient to obtain a final Building Regulations certificate, particularly in relation to the installation of wall ties and lintels. The appropriate measure of damages is the cost of remedial works based on the 'budget cost' option, including complete re-pointing, as well as damages for distress, inconvenience, and temporary relocation. It was reasonable for the defendants to refuse to allow the claimant to carry out the remedial works due to loss of trust. The counterclaim exceeds the amount of the claim, resulting in the claim failing by way of set-off.
Court Disposition
Claim dismissed by set-off; counterclaim allowed in part
Orders
- Claimant's claim for the final invoice is dismissed by set-off against the counterclaim.
- Defendants awarded damages for remedial works based on the budget cost option, including complete re-pointing.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment