Skanska Construction UK Ltd v Egger (Barony) Ltd. [2004] EWHC 1748 (TCC) (30 July 2004)
The court held that SCL was entitled to recover for those items which constituted changes outside the original Employer's Requirements, as opposed to mere detailing, and that fair valuation principles applied where no directly comparable rates existed. The court accepted the evidence of SCL's experts where supported and rejected claims or credits not substantiated by evidence. The court made detailed findings on each head of claim, awarding sums where justified and rejecting or reducing claims where not proven or where credits were due to Egger.
- Citation
- [2004] EWHC 1748 (TCC)
- Parties
- Claimant: Skanska Construction UK Limited (Formerly Kvaerner Construction Limited); Defendant: Egger (Barony) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 July 2004
- Procedural Posture
- Construction Dispute (quantum Trial) / Judgment on Quantum Following Earlier Liability Judgment
- Outcome
- Partially allowed; quantum awarded for proven claims, some claims rejected or reduced, credits given to defendant where appropriate.
- Legal Topics
- Quantum Meruit, Valuation of Variations, Interpretation of Contract Terms, Design and Build Contracts, Employer's Requirements, Tender Allowances, Change and Detailing Distinction
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Skanska Construction UK Limited (Formerly Kvaerner Construction Limited)
Claimant
Egger (Barony) Limited
Defendant
Procedural Posture
Construction Dispute (quantum Trial) / Judgment on Quantum Following Earlier Liability Judgment
Legal Issues
- 1 Proper valuation of quantum claims under a GMP construction contract
- 2 Distinction between changes and detailing under contract clause 1.16.1
- 3 Entitlement to payment for variations and additional works
Ratio Decidendi
The court held that SCL was entitled to recover for those items which constituted changes outside the original Employer's Requirements, as opposed to mere detailing, and that fair valuation principles applied where no directly comparable rates existed. The court accepted the evidence of SCL's experts where supported and rejected claims or credits not substantiated by evidence. The court made detailed findings on each head of claim, awarding sums where justified and rejecting or reducing claims where not proven or where credits were due to Egger.
Court Disposition
Partially allowed; quantum awarded for proven claims, some claims rejected or reduced, credits given to defendant where appropriate.
Orders
- SCL awarded specific sums for proven heads of claim as detailed in the judgment, including but not limited to: £125,779.83 for removal of spoil (Claim H1), £100,587.48 for temporary fire fighting (Claim H3), £36,337.20 for machine bases: silos (Claim H4A), £137,744.00 for machine bases: others (Claim H4), and...
- Credits and deductions applied to Egger where claims were not made out or where savings accrued from instructed changes.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment