Galliford Try Building Ltd v Estura Ltd
Summary judgment must be granted to enforce the adjudicator's decision because Estura failed to serve the required notices and raised no valid defence. However, due to the exceptional financial circumstances and risk of manifest injustice, enforcement is stayed above £1.5 million, subject to conditions, to balance the interests of both parties.
- Parties
- Claimant: Galliford Try Building Ltd; Defendant: Estura Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 27 February 2015
- Procedural Posture
- Civil (construction Contract Dispute) / Application for Summary Judgment to Enforce Adjudicator's Decision
- Outcome
- Summary judgment granted for the claimant; enforcement stayed above £1.5 million subject to conditions.
- Legal Topics
- Adjudication Enforcement, Interim Payments, Summary Judgment, Stay of Execution, Payment Notices, Pay Less Notices
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Galliford Try Building Ltd
Claimant
Estura Ltd
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Application for Summary Judgment to Enforce Adjudicator's Decision
Legal Issues
- 1 Whether summary judgment should be granted to enforce the adjudicator's decision for payment under an interim application where the employer failed to serve payment or pay less notices
- 2 Whether enforcement should be stayed due to alleged manifest injustice and the financial position of the defendant
Ratio Decidendi
Summary judgment must be granted to enforce the adjudicator's decision because Estura failed to serve the required notices and raised no valid defence. However, due to the exceptional financial circumstances and risk of manifest injustice, enforcement is stayed above £1.5 million, subject to conditions, to balance the interests of both parties.
Court Disposition
Summary judgment granted for the claimant; enforcement stayed above £1.5 million subject to conditions.
Orders
- Summary judgment for Galliford Try Building Ltd in the sum of £3,928,227.04 plus VAT (where applicable and to be assessed), plus interest of £33,739.78 and further interest at £591.92 per day until payment.
- Enforcement of the judgment is stayed above £1,500,000 until further order, subject to conditions regarding VAT invoice and possible variation if Estura's financial position changes or Galliford Try serves its Final Statement.
Full Case Text
Judgment text and source record