Ground Developments Ltd v FCC Construccion SA & Ors
The adjudicator was validly appointed under the Scheme, acted within jurisdiction, and decided the dispute referred (non-payment due to lack of Pay Less Notices). The procedural and jurisdictional objections raised by the Joint Venture were unfounded or insubstantial. There was no breach of natural justice. Summary judgment is granted to enforce the adjudicator's decision.
- Parties
- Claimant: Ground Developments LTD; Defendant: FCC Construccion SA; Defendant: Samsung C&T ECUK Limited; Defendant: Kier Infrastructure and Overseas Limited; Defendant: Merseylink Civil Contractors JV
- Jurisdiction
- England and Wales
- Judgment Date
- 27 July 2016
- Procedural Posture
- Civil (construction Adjudication Enforcement) / Summary Judgment Application
- Outcome
- Summary judgment granted for the claimant; adjudicator's decision enforced.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Natural Justice, Summary Judgment, Contract Formation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Ground Developments LTD
Claimant
FCC Construccion SA
Defendant
Samsung C&T ECUK Limited
Defendant
Kier Infrastructure and Overseas Limited
Defendant
Merseylink Civil Contractors JV
Defendant
Procedural Posture
Civil (construction Adjudication Enforcement) / Summary Judgment Application
Legal Issues
- 1 Whether the adjudicator's decision should be enforced by summary judgment
- 2 Whether the adjudicator acted within jurisdiction and in accordance with natural justice
- 3 Whether the correct adjudication procedure was followed given uncertainty over contract terms
Ratio Decidendi
The adjudicator was validly appointed under the Scheme, acted within jurisdiction, and decided the dispute referred (non-payment due to lack of Pay Less Notices). The procedural and jurisdictional objections raised by the Joint Venture were unfounded or insubstantial. There was no breach of natural justice. Summary judgment is granted to enforce the adjudicator's decision.
Court Disposition
Summary judgment granted for the claimant; adjudicator's decision enforced.
Orders
- Defendants to pay the sum of £207,403.27 plus VAT to the claimant.
- Court to hear further submissions on interest and costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment