Elements (Europe) Ltd v FK Building Ltd [2023] EWHC 726 (TCC) (30 March 2023)

Elements (Europe) Ltd v FK Building Ltd [2023] EWHC 726 (TCC) (30 March 2023)

A payment application received by email at any time on the fourth day prior to the interim valuation date is valid under the contract, as the law does not count fractions of a day and the contract did not require 'clear days' or restrict service to site working hours.

Source-derived case information.

Citation
[2023] EWHC 726 (TCC)
Parties
Claimant: Elements (Europe) Limited; Defendant: FK Building Limited; Claimant: FK Building Limited; Defendant: Elements (Europe) Limited
Jurisdiction
England and Wales
Judgment Date
30 March 2023
Procedural Posture
Adjudication Enforcement and Part 8 Claim / Summary Judgment and Declaratory Relief
Outcome
Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.
Legal Topics
Adjudication Enforcement, Payment Applications, Interpretation of Contract Terms, JCT Standard Building Sub Contract, Time for Service of Notices
Construction Law Contract Law Adjudication Enforcement Payment Applications Interpretation of Contract Terms JCT Standard Building Sub Contract Time for Service of Notices

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 12 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Elements (Europe) Limited

Claimant

FK Building Limited

Defendant

FK Building Limited

Claimant

Elements (Europe) Limited

Defendant

Procedural Posture

Adjudication Enforcement and Part 8 Claim / Summary Judgment and Declaratory Relief

  1. 1 Whether a payment application served by email at 22:07 on the relevant day was valid under the contract
  2. 2 Whether '4 days prior' in the contract means '4 clear days' or includes the fourth day
  3. 3 Whether service outside site working hours affects validity of payment application

Ratio Decidendi

A payment application received by email at any time on the fourth day prior to the interim valuation date is valid under the contract, as the law does not count fractions of a day and the contract did not require 'clear days' or restrict service to site working hours.

Court Disposition

Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.

Orders

  • Part 8 claim dismissed
  • Award enforceable in principle