Bend Weld Engineering Sdn Bhd v FMC Technologies Limited
The court found that BWE would likely be unable to satisfy a costs order, satisfying CPR 25.13(2)(c). However, security for costs should only cover costs incurred after commencement of proceedings up to the CMC, as pre-action costs were not shown to be purely defensive. The counterclaim is presently defensive and an undertaking was given to stay/dismiss it if the claim is dismissed for failure to provide security, justifying an order for security for costs.
- Parties
- Claimant: Bend Weld Engineering Sdn. Bhd; Defendant: FMC Technologies Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 October 2024
- Procedural Posture
- Civil (commercial/construction) / Interlocutory Application for Security for Costs
- Outcome
- Application for security for costs granted in part
- Legal Topics
- Security for Costs, Counterclaims, Costs Budgeting, Jurisdictional Requirements for Security
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Bend Weld Engineering Sdn. Bhd
Claimant
FMC Technologies Limited
Defendant
Procedural Posture
Civil (commercial/construction) / Interlocutory Application for Security for Costs
Legal Issues
- 1 Whether the defendant is entitled to security for costs under CPR 25.12 and 25.13
- 2 Whether the existence and nature of a counterclaim affects entitlement to security for costs
- 3 Whether pre-action costs should be included in a security for costs order
Ratio Decidendi
The court found that BWE would likely be unable to satisfy a costs order, satisfying CPR 25.13(2)(c). However, security for costs should only cover costs incurred after commencement of proceedings up to the CMC, as pre-action costs were not shown to be purely defensive. The counterclaim is presently defensive and an undertaking was given to stay/dismiss it if the claim is dismissed for failure to provide security, justifying an order for security for costs.
Court Disposition
Application for security for costs granted in part
Orders
- BWE to provide security for FMC’s costs up to the conclusion of the CMC in the sum of £70,800.
- No security ordered for pre-action costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment