Able Construction (UK) Ltd v Forest Property Development Ltd [2009] EWHC 159 (TCC) (27 January 2009)
The claimant is entitled to summary judgment for the unpaid balance under the Settlement Agreement and the adjudicator's decision, as the defendant is in breach and no valid defence or subsequent binding agreement was established.
- Citation
- [2009] EWHC 159 (TCC)
- Parties
- Claimant: Able Construction (UK) Ltd.; Defendant: Forest Property Development Ltd.
- Jurisdiction
- England and Wales
- Judgment Date
- 27 January 2009
- Procedural Posture
- Adjudication Enforcement Application Under CPR Part 24 / Summary Judgment Application
- Outcome
- Judgment for the claimant
- Legal Topics
- Adjudication Enforcement, Settlement Agreements, Summary Judgment, Interest on Commercial Debts, Indemnity Costs
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Able Construction (UK) Ltd.
Claimant
Forest Property Development Ltd.
Defendant
Procedural Posture
Adjudication Enforcement Application Under CPR Part 24 / Summary Judgment Application
Legal Issues
- 1 Whether the claimant is entitled to summary judgment to enforce an adjudicator's decision following breach of a settlement agreement
- 2 Whether a subsequent oral agreement altered the payment terms under the settlement agreement
- 3 Whether the court should award interest and indemnity costs
Ratio Decidendi
The claimant is entitled to summary judgment for the unpaid balance under the Settlement Agreement and the adjudicator's decision, as the defendant is in breach and no valid defence or subsequent binding agreement was established.
Court Disposition
Judgment for the claimant
Orders
- Judgment for Able Construction (UK) Ltd. in the sum of £100,613.69
- Interest awarded under the Late Payment of Commercial Debts (Interest) Act 1998
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment