Bridgewater Canal Company Ltd v Geo Networks Ltd [2010] EWHC 548 (Ch) (19 March 2010)
The Court held that under the Electronic Communications Code, paragraph 13(2)(e)(ii), the consideration payable is not limited to the right to carry out the installation works but also includes the right to keep the apparatus (cable) in place after installation. The statutory scheme confers a compendious right to install and keep apparatus, and the arbitrator erred in limiting payment to the installation process alone. The arbitrator's award was therefore set aside, and the matter remitted for reconsideration in accordance with this interpretation.
- Citation
- [2010] EWHC 548 (Ch)
- Parties
- Claimant: The Bridgewater Canal Company Limited; Defendant: GEO Networks Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 19 March 2010
- Procedural Posture
- Arbitration Appeal (chancery Division, High Court) / Judgment on Appeal From Arbitration Award
- Outcome
- Appeal allowed. Arbitration award set aside.
- Legal Topics
- Electronic Communications Code, Linear Obstacles, Statutory Rights of Telecommunications Operators, Compensation and Consideration for Land Rights, Arbitration Under Statutory Codes
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
The Bridgewater Canal Company Limited
Claimant
GEO Networks Limited
Defendant
Procedural Posture
Arbitration Appeal (chancery Division, High Court) / Judgment on Appeal From Arbitration Award
Legal Issues
- 1 Whether the operator must pay consideration for the right to keep apparatus (cables) under a canal after installation, or only for the right to carry out the installation works under the Electronic Communications Code, paragraphs 12 and 13.
Ratio Decidendi
The Court held that under the Electronic Communications Code, paragraph 13(2)(e)(ii), the consideration payable is not limited to the right to carry out the installation works but also includes the right to keep the apparatus (cable) in place after installation. The statutory scheme confers a compendious right to install and keep apparatus, and the arbitrator erred in limiting payment to the installation process alone. The arbitrator's award was therefore set aside, and the matter remitted for reconsideration in accordance with this interpretation.
Court Disposition
Appeal allowed. Arbitration award set aside.
Orders
- The arbitrator's award is set aside.
- The matter is remitted to the arbitrator for reconsideration in accordance with the Court's judgment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment