North Midland Construction Plc v Geo Networks Ltd [2015] EWHC 3063 (TCC) (30 October 2015)
Claimant's conduct justified Defendant's applications; Defendant entitled to costs in both claims, with solicitors' costs reduced proportionally and counsel's fees deemed reasonable.
- Citation
- [2015] EWHC 3063 (TCC)
- Parties
- Claimant: North Midland Construction plc; Defendant: Geo Networks Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 30 October 2015
- Procedural Posture
- Costs Determination Following Applications to Strike Out and for Relief From Sanctions / Post Judgment, Costs Assessment
- Outcome
- Costs summarily assessed and awarded to Defendant in both claims.
- Legal Topics
- Relief From Sanctions, Strike Out Applications, Costs Assessment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
North Midland Construction plc
Claimant
Geo Networks Ltd
Defendant
Procedural Posture
Costs Determination Following Applications to Strike Out and for Relief From Sanctions / Post Judgment, Costs Assessment
Legal Issues
- 1 Whether costs should be summarily assessed or subject to detailed assessment
- 2 Who should bear the costs of the applications in both claims
Ratio Decidendi
Claimant's conduct justified Defendant's applications; Defendant entitled to costs in both claims, with solicitors' costs reduced proportionally and counsel's fees deemed reasonable.
Court Disposition
Costs summarily assessed and awarded to Defendant in both claims.
Orders
- Claimant to pay Defendant £17,850 in Fibrespeed claim within 14 days.
- Claimant to pay Defendant £18,750.88 in Project Yellow claim within 14 days.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment