Walter Lilly & Company Ltd v Mackay & Anor
WLC is entitled to an extension of time through to 7 July 2008 due to employer-responsible delays, including late instructions and variations. WLC's loss and expense claims, though global in nature, are recoverable as the delays and additional costs were caused by employer-responsible events and properly evidenced. WLC is not liable for the major defects (ABW, Light Wall, Courtyard Sliding Doors) as no design responsibility was transferred. DMW's counterclaims for defects are extinguished or reduced by the settlement sums received from third parties. WLC is entitled to payment for omitted works, sub-contractor settlements, and interest on late payments at the contractual rate.
- Parties
- Claimant: Walter Lilly & Company Limited; Defendant: Giles Patrick Cyril Mackay; Defendant: DMW Developments Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 July 2012
- Procedural Posture
- Civil (construction Dispute) / Judgment After Full Trial
- Outcome
- Judgment for the claimant (WLC)
- Legal Topics
- Extensions of Time, Loss and Expense Claims, Global Claims, Concurrent Delay, Design Responsibility, Liquidated Damages, Defects Liability, Settlement Credits
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Walter Lilly & Company Limited
Claimant
Giles Patrick Cyril Mackay
Defendant
DMW Developments Limited
Defendant
Procedural Posture
Civil (construction Dispute) / Judgment After Full Trial
Legal Issues
- 1 Whether the claimant is entitled to extensions of time for delays caused by the employer and its design team.
- 2 Whether the claimant is entitled to recover loss and expense for delay and disruption, including global claims.
- 3 Whether the claimant is liable for alleged defects (ABW, Light Wall, Courtyard Sliding Doors, etc).
Ratio Decidendi
WLC is entitled to an extension of time through to 7 July 2008 due to employer-responsible delays, including late instructions and variations. WLC's loss and expense claims, though global in nature, are recoverable as the delays and additional costs were caused by employer-responsible events and properly evidenced. WLC is not liable for the major defects (ABW, Light Wall, Courtyard Sliding Doors) as no design responsibility was transferred. DMW's counterclaims for defects are extinguished or reduced by the settlement sums received from third parties. WLC is entitled to payment for omitted works, sub-contractor settlements, and interest on late payments at the contractual rate.
Court Disposition
Judgment for the claimant (WLC)
Orders
- WLC awarded £2,330,666.26 (exclusive of contractual interest) against DMW.
- DMW's counterclaims for defects and liquidated damages dismissed or reduced by settlement credits.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment