Walter Lilly & Company Ltd v Mackay & Anor [2012] EWHC 1773 (TCC) (11 July 2012)
Delays were primarily caused by late instructions, incomplete design, and poor coordination by DMW and its professional team, not by Walter Lilly & Company Limited. WLC is entitled to extensions of time and loss and expense for such delays. Liquidated damages imposed by DMW are not valid for periods where delay was not culpable on WLC's part. Design responsibility was not properly allocated to WLC except for piling; employer retains risk for undefined provisional sums. Defective works claims must be assessed against contractual specification and industry standards; most defects alleged were not proven against WLC.
- Citation
- [2012] EWHC 1773 (TCC)
- Parties
- Claimant: Walter Lilly & Company Limited; Defendant: Giles Patrick Cyril Mackay; Defendant: DMW Developments Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 July 2012
- Procedural Posture
- Construction Dispute / High Court Judgment
- Outcome
- Judgment for claimant
- Legal Topics
- Delay Analysis, Extensions of Time, Liquidated Damages, Global Claims, Contractor Design Responsibility, Defective Works, Quantum Claims
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Walter Lilly & Company Limited
Claimant
Giles Patrick Cyril Mackay
Defendant
DMW Developments Limited
Defendant
Procedural Posture
Construction Dispute / High Court Judgment
Legal Issues
- 1 Responsibility for delays and extensions of time
- 2 Entitlement to loss and expense
- 3 Allocation of design responsibility
Ratio Decidendi
Delays were primarily caused by late instructions, incomplete design, and poor coordination by DMW and its professional team, not by Walter Lilly & Company Limited. WLC is entitled to extensions of time and loss and expense for such delays. Liquidated damages imposed by DMW are not valid for periods where delay was not culpable on WLC's part. Design responsibility was not properly allocated to WLC except for piling; employer retains risk for undefined provisional sums. Defective works claims must be assessed against contractual specification and industry standards; most defects alleged were not proven against WLC.
Court Disposition
Judgment for claimant
Orders
- Extensions of time granted to Walter Lilly & Company Limited
- DMW Developments Limited to pay sums due for works completed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment