Global Energy Horizons Corporation v Gray

Global Energy Horizons Corporation v Gray

The Court of Appeal held that GEHC was the clear winner of the Enquiry Phase, having obtained a substantial monetary award and exposed Mr Gray's dishonest account. The trial judge erred in principle by failing to give sufficient weight to Mr Gray's conduct as a defaulting fiduciary and by treating the outcome as a...

Source-derived case information.

Parties
Appellant: Global Energy Horizons Corporation; Respondent: Robert Gresham Gray
Jurisdiction
England and Wales
Judgment Date
05 February 2021
Procedural Posture
Civil Appeal / Costs Determination on Appeal
Outcome
appeal allowed in part
Legal Topics
Costs, Fiduciary Duty, Valuation of Assets
Civil Procedure Trusts and Equity Costs Fiduciary Duty Valuation of Assets

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Global Energy Horizons Corporation

Appellant

Robert Gresham Gray

Respondent

Procedural Posture

Civil Appeal / Costs Determination on Appeal

  1. 1 Whether the trial judge erred in making no order as to costs for the Enquiry Phase
  2. 2 Whether the appellant was the successful party for costs purposes
  3. 3 Whether the conduct of the respondent as a defaulting fiduciary should affect the costs order

Ratio Decidendi

The Court of Appeal held that GEHC was the clear winner of the Enquiry Phase, having obtained a substantial monetary award and exposed Mr Gray's dishonest account. The trial judge erred in principle by failing to give sufficient weight to Mr Gray's conduct as a defaulting fiduciary and by treating the outcome as a 'score draw.' The proper order was for Mr Gray to pay GEHC's costs of the Enquiry Phase, except for the fees and disbursements relating to valuation experts, reflecting the part of the proceedings on which Mr Gray succeeded.

Court Disposition

appeal allowed in part

Orders

  • Paragraph 6 of the order of 4 October 2019 set aside and substituted with an order that Mr Gray pay GEHC’s costs of the Enquiry Trial Phase except for the fees and disbursements paid to Dr Stephen Becker or Dr Larry Lake.
  • The Enquiry Trial Phase defined as all proceedings in the account of profits up to and including 28 July 2015 and, for the period between 28 July 2015 and the 2016 Asplin Order, the costs of and occasioned by the management fee calculation.