BioConstruct Ltd v Grays Thurrock Properties Ltd
BioConstruct's interpretation of 'immediately preceding' is supported by authority and gives it a real prospect of success; the Application to strike out or summarily dismiss the claim is dismissed as the claim is properly pleaded and not doomed to failure.
- Parties
- Claimant: BioConstruct Ltd; Defendant: Grays Thurrock Properties Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 28 November 2025
- Procedural Posture
- Strike Out Application / Interlocutory Application Before Trial
- Outcome
- Application dismissed
- Legal Topics
- Milestone Contracts, Summary Judgment, Strike Out Applications, Pleading Requirements, Interpretation of Contractual Terms
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
BioConstruct Ltd
Claimant
Grays Thurrock Properties Ltd
Defendant
Procedural Posture
Strike Out Application / Interlocutory Application Before Trial
Legal Issues
- 1 Whether BioConstruct's claim for payment under Milestone 14 and subsequent milestones should be struck out or summarily dismissed
- 2 Whether the interpretation of 'immediately preceding' in the Subcontract precludes BioConstruct's claim
- 3 Whether matters pleaded in the Reply can remedy deficiencies in the Particulars of Claim
Ratio Decidendi
BioConstruct's interpretation of 'immediately preceding' is supported by authority and gives it a real prospect of success; the Application to strike out or summarily dismiss the claim is dismissed as the claim is properly pleaded and not doomed to failure.
Court Disposition
Application dismissed
Orders
- Application for strike out and/or summary judgment is dismissed
- Costs to be agreed or determined by the Court if not agreed
Full Case Text
Judgment text and source record