Working Environments Ltd v Greencoat Construction Ltd [2012] EWHC 1039 (TCC) (24 April 2012)
A crystallised dispute existed as to the sums due under the interim application and the items of set-off identified prior to adjudication; the adjudicator had jurisdiction to decide on those items (1-10), but not on items 11 and 12, which were not part of the crystallised dispute. The decision is severable, and the enforceable part (excluding items 11 and 12) is binding and must be paid.
- Citation
- [2012] EWHC 1039 (TCC)
- Parties
- Claimant: Working Environments Limited; Defendant: Greencoat Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 24 April 2012
- Procedural Posture
- Adjudication Enforcement / Summary Judgment / High Court (tcc) Judgment on Enforcement of Adjudicator's Decision
- Outcome
- Judgment for the Claimant (Working Environments Limited) for the enforceable part of the adjudicator's decision, with severance of items outside jurisdiction.
- Legal Topics
- Adjudication Enforcement, Crystallisation of Disputes, Jurisdiction of Adjudicator, Severability of Adjudicator's Decision, Withholding Notices, Set Off, Declaratory Relief
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Working Environments Limited
Claimant
Greencoat Construction Limited
Defendant
Procedural Posture
Adjudication Enforcement / Summary Judgment / High Court (tcc) Judgment on Enforcement of Adjudicator's Decision
Legal Issues
- 1 Whether a dispute had crystallised prior to adjudication
- 2 Whether the adjudicator had jurisdiction to decide all items in the Withholding Notice, particularly items 11 and 12
- 3 Whether the adjudicator's decision could be severed to enforce only the part within jurisdiction
Ratio Decidendi
A crystallised dispute existed as to the sums due under the interim application and the items of set-off identified prior to adjudication; the adjudicator had jurisdiction to decide on those items (1-10), but not on items 11 and 12, which were not part of the crystallised dispute. The decision is severable, and the enforceable part (excluding items 11 and 12) is binding and must be paid.
Court Disposition
Judgment for the Claimant (Working Environments Limited) for the enforceable part of the adjudicator's decision, with severance of items outside jurisdiction.
Orders
- Defendant (Greencoat Construction Limited) to pay £291,331.20 to the Claimant, comprising £229,711 plus VAT (£275,653.20) and 65% of the adjudicator's fee (£15,678)
- Interest awarded at 3% from 1 March 2012 to 24 April 2012
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment