Working Environments Ltd v Greencoat Construction Ltd
A crystallised dispute existed as to the sums due under Application No. 10, including the first ten items of the Withholding Notice. The adjudicator had jurisdiction to determine those items but not items 11 and 12, which were not part of the crystallised dispute at the time of referral. The adjudicator's decision was severable, and the court enforced the part within jurisdiction, reducing the sum by the value of items 11 and 12.
- Parties
- Claimant: Working Environments Limited; Defendant: Greencoat Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 24 April 2012
- Procedural Posture
- Civil (construction Dispute) / Judgment on Summary Enforcement of Adjudicator's Decision
- Outcome
- Judgment for the claimant (Working Environments Limited) for the sum within the adjudicator's jurisdiction, with costs and interest.
- Legal Topics
- Adjudication Enforcement, Crystallisation of Disputes, Jurisdiction of Adjudicator, Severability of Adjudicator's Decision, Withholding Notices, Set Off, Declaratory Relief
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Working Environments Limited
Claimant
Greencoat Construction Limited
Defendant
Procedural Posture
Civil (construction Dispute) / Judgment on Summary Enforcement of Adjudicator's Decision
Legal Issues
- 1 Whether a dispute had crystallised prior to adjudication
- 2 Whether the adjudicator had jurisdiction to determine all items in the Withholding Notice, specifically items 11 and 12
- 3 Whether the adjudicator's decision could be severed to enforce only the part within jurisdiction
Ratio Decidendi
A crystallised dispute existed as to the sums due under Application No. 10, including the first ten items of the Withholding Notice. The adjudicator had jurisdiction to determine those items but not items 11 and 12, which were not part of the crystallised dispute at the time of referral. The adjudicator's decision was severable, and the court enforced the part within jurisdiction, reducing the sum by the value of items 11 and 12.
Court Disposition
Judgment for the claimant (Working Environments Limited) for the sum within the adjudicator's jurisdiction, with costs and interest.
Orders
- Judgment for Working Environments Limited against Greencoat Construction Limited in the sum of £291,331.20
- Interest awarded at 3% from 1 March 2012 to 24 April 2012
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment