North Principal Investment Fund Ltd v Greenoak Renewable Energy
Given the seriously arguable case for the claimant's entitlement to a 50% equity interest and/or a veto over sale, and the inadequacy of damages as a remedy due to quantification difficulties and lack of evidence of the defendant's financial standing, the court granted an interim injunction restraining the defendant from disposing of its interest without the claimant's consent or leave of the court, with protection for the defendant via a cross-undertaking in damages fortified by retention of €10 million in London.
- Parties
- Claimant: North Principal Investment Fund Ltd; Defendant: Greenoak Renewable Energy
- Jurisdiction
- England and Wales
- Judgment Date
- 31 January 2008
- Procedural Posture
- Application for Interim Injunction / Interlocutory
- Outcome
- Interim injunction granted in terms of paragraph 1 of the claimant's proposed order; orders sought in paragraphs 2 and 3 declined.
- Legal Topics
- Interim Injunctions, Assignment of Contractual Rights, Balance of Convenience, Adequacy of Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
North Principal Investment Fund Ltd
Claimant
Greenoak Renewable Energy
Defendant
Procedural Posture
Application for Interim Injunction / Interlocutory
Legal Issues
- 1 Whether the claimant is entitled to an interim injunction restraining the defendant from disposing of its interest in the project.
- 2 Whether damages would be an adequate remedy for the claimant if no injunction is granted.
- 3 Whether the claimant is entitled to information regarding any proposed sale of the defendant's interest in the project.
Ratio Decidendi
Given the seriously arguable case for the claimant's entitlement to a 50% equity interest and/or a veto over sale, and the inadequacy of damages as a remedy due to quantification difficulties and lack of evidence of the defendant's financial standing, the court granted an interim injunction restraining the defendant from disposing of its interest without the claimant's consent or leave of the court, with protection for the defendant via a cross-undertaking in damages fortified by retention of €10 million in London.
Court Disposition
Interim injunction granted in terms of paragraph 1 of the claimant's proposed order; orders sought in paragraphs 2 and 3 declined.
Orders
- Defendant restrained until judgment or further order from disposing of, agreeing to dispose of, or encumbering any part of its share capital, business, or assets, including any interest in the project, without claimant's written consent or leave of the court.
- Claimant to give cross-undertaking in damages, fortified by retention of €10 million in London as described.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment