Pearson Pension Funds v Gurney Consultants

Pearson Pension Funds v Gurney Consultants

Permission to amend is granted only where the amendments do not risk the trial date or cause irredeemable prejudice; amendments raising entirely new issues late in proceedings are refused if they would require disproportionate additional work and jeopardize trial readiness.

Source-derived case information.

Parties
Claimant: Pearson Pension Funds; Defendant: Gurney Consultants
Jurisdiction
England and Wales
Judgment Date
01 December 2005
Procedural Posture
Civil / Interlocutory Application for Permission to Amend Pleadings
Outcome
Permission granted in part; amendments allowed for Quantum Point 1, refused for Points 2 and 3.
Legal Topics
Late Amendments, Expert Evidence, Quantum of Damages, Breach of Duty, Loss of Rent
Civil Procedure Construction Law Professional Negligence Late Amendments Expert Evidence Quantum of Damages Breach of Duty Loss of Rent

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Pearson Pension Funds

Claimant

Gurney Consultants

Defendant

Procedural Posture

Civil / Interlocutory Application for Permission to Amend Pleadings

  1. 1 Whether late amendments to pleadings should be permitted
  2. 2 Whether amendments would cause irredeemable prejudice or risk the trial date
  3. 3 Whether parties can adequately respond to new allegations before trial

Ratio Decidendi

Permission to amend is granted only where the amendments do not risk the trial date or cause irredeemable prejudice; amendments raising entirely new issues late in proceedings are refused if they would require disproportionate additional work and jeopardize trial readiness.

Court Disposition

Permission granted in part; amendments allowed for Quantum Point 1, refused for Points 2 and 3.

Orders

  • Gurney to provide supporting material for notional completion dates by 4.00 p.m. on 2nd December 2005.
  • Permission to rely on expert programming evidence limited to material provided by deadline.