WRB (NI) Ltd v Henry Construction Projects Ltd [2023] EWHC 278 (TCC) (10 February 2023)

WRB (NI) Ltd v Henry Construction Projects Ltd [2023] EWHC 278 (TCC) (10 February 2023)

Summary judgment is granted for the principal sum and adjudicator's fees because Henry Construction contracted with a dormant company at its own risk and there is no evidence of a material change in WRB's financial position since contract formation; a stay of execution is refused as it would be contrary to the spirit of adjudication enforcement and the risk is inherent in Henry Construction's own contracting decision.

Citation
[2023] EWHC 278 (TCC)
Parties
Claimant: WRB (N. I.) Limited; Defendant: Henry Construction Projects Limited
Jurisdiction
England and Wales
Judgment Date
10 February 2023
Procedural Posture
Summary Judgment Application to Enforce Adjudicator's Decision / Judgment After Hearing of Summary Judgment Application and Cross Application for Stay
Outcome
Summary judgment granted for WRB (N. I.) Limited; application for stay of execution dismissed.
Legal Topics
Adjudication Enforcement, Stay of Execution, Summary Judgment, Dormant Company Contracting, VAT Entitlement

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 10 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

WRB (N. I.) Limited

Claimant

Henry Construction Projects Limited

Defendant

Procedural Posture

Summary Judgment Application to Enforce Adjudicator's Decision / Judgment After Hearing of Summary Judgment Application and Cross Application for Stay

  1. 1 Whether summary judgment should be granted to enforce the adjudicator's decision
  2. 2 Whether a stay of execution should be granted due to the claimant's financial position and potential cross-claims
  3. 3 Whether VAT is payable on the adjudicator's award

Ratio Decidendi

Summary judgment is granted for the principal sum and adjudicator's fees because Henry Construction contracted with a dormant company at its own risk and there is no evidence of a material change in WRB's financial position since contract formation; a stay of execution is refused as it would be contrary to the spirit of adjudication enforcement and the risk is inherent in Henry Construction's own contracting decision.

Court Disposition

Summary judgment granted for WRB (N. I.) Limited; application for stay of execution dismissed.

Orders

  • Henry Construction Projects Limited to pay WRB (N. I.) Limited £120,752.14 plus interest of £271.26 to the date of judgment.
  • Henry Construction Projects Limited to reimburse WRB (N. I.) Limited £18,775.80 for adjudicator's fees and expenses.