Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) [2007] EWHC 447 (TCC) (06 March 2007)
Directions issued by Multiplex under clause 4.2, which constitute variations and cause delay, are acts of prevention within the meaning of clause 11.10.7. However, such acts do not set time at large because clause 11 provides a mechanism for extension of time in respect of those events. The extension of time machinery remains operable, and time is not at large. Multiplex is entitled to the declarations sought on the construction point.
- Citation
- [2007] EWHC 447 (TCC)
- Parties
- Claimant: Multiplex Constructions (UK) Limited; Defendant: Honeywell Control Systems Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 06 March 2007
- Procedural Posture
- Claim for Declarations (construction Dispute) / High Court (technology & Construction Court) Judgment
- Outcome
- Declarations granted in favour of Multiplex; time not at large under the sub-contract.
- Legal Topics
- Extension of Time, Prevention Principle, Time at Large, Construction Contracts, Sub Contractor Obligations, Programming and Delay
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Multiplex Constructions (UK) Limited
Claimant
Honeywell Control Systems Limited
Defendant
Procedural Posture
Claim for Declarations (construction Dispute) / High Court (technology & Construction Court) Judgment
Legal Issues
- 1 Whether time has been set at large under the sub-contract due to directions issued under clause 4.2; Whether the extension of time mechanism in clause 11 is operable; Whether Multiplex's conduct made the extension of time machinery inoperable; Whether failure to comply with condition precedent in clause 11.1.3 puts time at large; Effect of the settlement agreement between Multiplex and WNSL on time for completion.
Ratio Decidendi
Directions issued by Multiplex under clause 4.2, which constitute variations and cause delay, are acts of prevention within the meaning of clause 11.10.7. However, such acts do not set time at large because clause 11 provides a mechanism for extension of time in respect of those events. The extension of time machinery remains operable, and time is not at large. Multiplex is entitled to the declarations sought on the construction point.
Court Disposition
Declarations granted in favour of Multiplex; time not at large under the sub-contract.
Orders
- It is declared that clause 11 provides a mechanism for extending the period for completion in respect of delay caused by instructions under clause 4.2.
- It is declared that directions under clause 4.2 do not render time at large.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment