Yoram Amsalem (t/a MRE Building Contractors) v Raivid & Anor [2008] EWHC 3028 (TCC) (09 December 2008)
No lump sum or capped contract was agreed; works were carried out on a reasonable price basis. The defendants repudiated the contract by denying access to the site. The claimant is entitled to payment for the value of works completed, assessed on quantum meruit, less sums paid and defects. No economic duress was established regarding fittings. Damages for delay are not awarded due to lack of evidence.
- Citation
- [2008] EWHC 3028 (TCC)
- Parties
- Claimant: Yoram Amsalem (trading as MRE Building Contractors); Defendant: Hugh Mark Raivid; Defendant: Marsha Raivid
- Jurisdiction
- England and Wales
- Judgment Date
- 09 December 2008
- Procedural Posture
- Civil Construction Dispute / Final Judgment After Trial
- Outcome
- Judgment for the Claimant
- Legal Topics
- Formation of Contract, Variation of Contract, Repudiation, Quantum Meruit, Economic Duress, Defective Works, Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Yoram Amsalem (trading as MRE Building Contractors)
Claimant
Hugh Mark Raivid
Defendant
Marsha Raivid
Defendant
Procedural Posture
Civil Construction Dispute / Final Judgment After Trial
Legal Issues
- 1 Was there a lump sum contract or capped agreement for the works?
- 2 Were additional works and variations agreed, and at what price?
- 3 What sums are due for extras?
Ratio Decidendi
No lump sum or capped contract was agreed; works were carried out on a reasonable price basis. The defendants repudiated the contract by denying access to the site. The claimant is entitled to payment for the value of works completed, assessed on quantum meruit, less sums paid and defects. No economic duress was established regarding fittings. Damages for delay are not awarded due to lack of evidence.
Court Disposition
Judgment for the Claimant
Orders
- Defendants to pay claimant the reasonable value of works completed, less sums already paid and cost of defects.
- No damages awarded for delay.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment